You sent your application, the payment date came and went, and what arrived was less than you asked for with no explanation. On most construction work, other than work for a homeowner on their own home, the law does not allow that. The contractor has to tell you on time what they will pay and how they worked it out, and if they then want to pay less than that notified sum, they have to send a pay less notice, with their workings, before the final date for payment. If they do neither, they can end up owing the full amount you applied for.
These rules are in Part II of the Housing Grants, Construction and Regeneration Act 1996 (often called the Construction Act), as amended in 2011, and in the Scheme for Construction Contracts, which fills any gaps in your contract. Both were checked on legislation.gov.uk on 16 November 2026. This guide covers England and Wales: the Scheme was amended separately for each in 2011, with the same payment dates. Scotland has its own Scheme, so check that if you work there. It is a summary, not legal advice.
Which work is covered
The payment rules apply to construction contracts: building, altering, repairing, decorating, installing heating, electrics, plumbing and drainage, groundworks, scaffolding and landscaping that is part of construction work, among other things listed in section 105. They apply to subcontracts as well as main contracts, and since the 2011 changes they apply whether or not the contract is written down.
Some work is excluded, including installing plant or machinery on sites whose main activity is power generation, water treatment, chemicals or food and drink, and supply-only contracts where you do not install what you deliver (section 105(2)).
They also do not apply to a contract with a residential occupier: one that principally relates to work on a house or flat that one of the parties lives in, or intends to live in (section 106). So a homeowner having their kitchen done is not covered, but a builder who hires you to work on that same kitchen is, because your contract is with the builder. A landlord who does not live in the property is covered too.
The five dates and notices
Every construction contract has to say what payments become due, when, and the final date for paying each one (section 110). If it does not, the Scheme fills the gap. In the order they happen:
- Your application. You tell the contractor what you think is due and how you worked it out. Under the Scheme this is a "claim by the payee": a written notice of the amount and its basis.
- The due date. The date the payment becomes due.
- The payment notice. Within five days of the due date, the contractor (or someone named in the contract, such as a quantity surveyor) must tell you the sum they consider due and how it was calculated (section 110A). The sum can be zero, but the notice still has to show the basis. If your contract says nothing about payment notices, the Scheme still requires one.
- The pay less notice. If the contractor intends to pay less than the notified sum, they must say so in a notice giving the sum they consider due and the basis for it, no later than the agreed period before the final date (section 111).
- The final date for payment. The last day the money can arrive without being late.
The notified sum is usually the figure in the contractor's payment notice. If their payment notice arrives on time with a lower figure than you applied for, and shows how it was worked out, that lower figure is the notified sum, and they do not need a pay less notice to pay it. You can still dispute it, but the rules below about missing notices do not apply. Your own figure only becomes the notified sum when no payment notice is sent.
Your contract can set its own dates for most of these. Where it does not, the Scheme sets them.
How the dates work if your contract is silent
Say your contract does not specify, and you have not agreed, that the job will take less than 45 days, and no payment dates are agreed. Under the Scheme, the period is 28 days, and you send your application on the last day of the period. Counting from that day:
| Day | What happens | Where it comes from |
|---|---|---|
| 0 | End of the period; you send your application | Scheme, paragraphs 2 and 12 |
| 7 | Payment becomes due (7 days after the period, or when you claim, whichever is later) | Scheme, paragraph 4 |
| 12 | Last day for the contractor's payment notice (5 days after the due date) | Scheme, paragraph 9 |
| 17 | Last day for a pay less notice (7 days before the final date) | Scheme, paragraph 10 |
| 24 | Final date for payment (17 days after the due date) | Scheme, paragraph 8 |
Counting starts the day after. Christmas Day, Good Friday and bank holidays are not counted (section 116), so the real dates move when one falls inside the period.
Two more things follow. A late application pushes everything back, because the due date is the later of the end of the period and your claim. And where the contract specifies, or you agree, that the work will take less than 45 days, you have no automatic right to stage payments (section 109); under the Scheme, the whole price becomes due 30 days after the work is finished or when you claim, whichever is later (paragraph 6), and the final date for paying it is 17 days after that.
If the contractor does not send a payment notice
If the contractor does not send a payment notice when the contract (or the Scheme) requires one, you can send your own notice of the sum you consider due and how you worked it out (section 110B). That becomes the notified sum, but the final date moves back by the number of days after the deadline that you sent it, so send it straight away.
If your contract lets you send your application before the payment notice deadline, and you sent it on time, in the way the contract requires and showing how you worked it out, you do not need a second notice. The Act treats your application as that notice, and the sum in it becomes the notified sum.
Either way, the contractor can still send a pay less notice afterwards, as long as it arrives before the pay less deadline, which moves with the final date. Keep watching for one.
If they pay less without a pay less notice
The contractor must pay the notified sum by the final date (section 111). A pay less notice is the only way to pay less than the notified sum, and it has to give the sum and the basis, and arrive on time. A short payment with no notice, a notice after the deadline, or one that gives a figure with no workings does not do that.
An example, with made-up figures: you are doing first fix electrics on a block of flats for a main contractor, and your subcontract lets you apply before the payment notice deadline. You send an application for £6,000 for the month on time, by the method the contract sets, with a breakdown. No payment notice arrives, so your application becomes the notified sum. On the final date, £4,500 arrives with an email saying some of the work was not up to standard, but no pay less notice came by the deadline. The notified sum is still £6,000, and you can ask for the other £1,500. The contractor can still dispute the quality of the work, but that is a separate argument; it does not let them hold back the money now.
What you can do about it
- Ask in writing. Point to the notified sum, the final date and the missing notice, and ask for the balance by a set date.
- Suspend work. If the notified sum is not paid by the final date, you can suspend some or all of your work after giving at least seven days' written notice of your intention, saying why (section 112). The contractor has to pay a reasonable amount for the costs and expenses you reasonably incur by suspending, and the time you are suspended does not count against your contract deadlines for the work affected. The right ends when they pay in full.
- Refer it to adjudication. Every construction contract gives you the right to refer a dispute to an adjudicator. The contract must aim to have an adjudicator appointed and the dispute referred within 7 days of your notice. The adjudicator must decide within 28 days of referral, which can be extended by 14 days with your consent, or for longer if both sides agree. The decision is binding unless and until a court, an arbitration or an agreement settles the dispute (section 108).
- Claim interest. On business debts, you may be able to claim statutory interest on late payment unless your contract sets its own rate. See chasing late invoices.
Suspension and adjudication have consequences for the working relationship and can carry costs, so speak to a construction solicitor or adviser before you use them.
"We pay when we get paid" is not allowed
A clause saying you are paid only when the contractor is paid by their client is ineffective, unless the client (or someone further up the chain) is insolvent (section 113). Where such a clause is struck out and nothing else is agreed, the Scheme's payment terms apply (paragraph 11). If a contractor tells you they cannot pay until the client pays them, that is not a reason the law accepts.
Where software helps
The method above works with a diary and a folder. If you run several subcontracts at once, job management or invoicing software that sets reminders against each job can track application dates and notice deadlines for you, and keep each notice with the job it belongs to.
What to do this week
- Find the payment terms in each of your current subcontracts: the period, the due date, the final date and the pay less notice period. Where there are none, use the Scheme's dates above.
- Put the application dates in your diary for each job, and send every application on time, in writing, with the amount and how you worked it out.
- Check whether your contract lets you apply before the payment notice deadline. If it does, always do, so your application stands if no notice comes.
- Keep every payment notice and pay less notice with the date it arrived, and check each against the deadlines, allowing for bank holidays.
- If a payment arrives short of the notified sum without a valid pay less notice, write to the contractor the same day, quoting the notified sum and the final date.
- Before suspending work or starting adjudication, get advice from a construction solicitor or adviser.