"How much for a full rewire?" is asked as if it has one answer, and the customer usually has not thought about whether they will be living there, how many sockets they want, or who plasters the chases afterwards. All three change the price, so ask them before you quote, price the job from a count of points plus the fixed parts, and write down what happens between first fix and second fix, and who makes good.
Three answers to get before you price
Will the house be empty or lived in? In an empty house you can lift floors and work room by room without moving anyone's furniture or keeping power on. In an occupied one, you are clearing and covering each room, putting it back each evening, and keeping lights and some sockets working while the old circuits come out. Ask, and write the answer on the quote, because it changes the number of days.
How many points, and where? A rewire is a good time to add sockets, move switches, or put a cable in for a car charger or garden lighting later. Walk round with the customer and mark what they want in each room. If they are not sure, quote your standard layout and list the extras as optional lines.
Who makes good, and who decorates? Chasing walls and lifting boards leaves work behind. If the plastering, filling and decorating are not yours, the quote has to say so in plain words, or the customer will assume they are.
Count the points, room by room
Build the quote from the walk-round. When the customer decides they want a double socket by the bed after all, you change one number and resend. A structure like this works whatever your rates:
| Line | Count it by | Notes |
|---|---|---|
| Circuits | Number of circuits | Name each: sockets per floor, lighting per floor, cooker, shower, immersion |
| Socket outlets | Number of points | Singles and doubles listed separately; note any USB or outdoor sockets |
| Lighting points and switches | Number of points | Note two-way switching and any downlights |
| Fixed appliances | Number | Cooker, hob, extractor fans, shower, immersion |
| Smoke and heat alarms | Number, or "not included" | Say whether they are in the price either way |
| Main bonding to gas and water | Per service | Included where the pipes can be reached; hidden runs priced as an extra |
| Data, TV and aerial | Number of points | Only if you are doing them |
| Strip-out | Per house | Old cable, accessories and the old board, and whether you take them away |
| Living-in allowance | Per day or per job | Clearing, covering and temporary supplies, if the house is occupied |
| Consumer unit, testing, certification and notification | Per job | Priced as set out in the consumer unit change guide |
If you take the old cable and the old board away, check your waste carrier registration; the bathroom refit guide sets out when you need to be upper tier.
First fix, second fix and the gap between
A rewire is two jobs with a gap in the middle. First fix is the cables, back boxes and chases; second fix is the accessories, connecting up the board, testing and certification. In between, someone has to plaster or fill the chases and make good the floors.
Put the gap on the quote:
- Who plasters, and when. If the customer's plasterer is doing it, say second fix starts when they have finished, and that a delay on their side moves your dates.
- What works in the meantime. If people are living there, say which lights and sockets will be live between the two fixes.
- A payment when first fix is done. First fix is where the cable and much of the labour go, so it is a natural point for a stage payment, due when you have finished it and before the walls are closed. The deposits guide covers building a schedule around stages like this, and what changes when the job is agreed in the customer's home.
One notification for the whole job
A full rewire installs new circuits, and usually a new board. The Planning Portal's guidance on electrics, checked on 17 November 2026, lists "the installation of a complete new circuit" and "the installation of a new consumer unit or fuse box" as notifiable jobs. The page covers England, notes that policy in Wales may differ, and gives no rules for Scotland or Northern Ireland, so if you work outside England, check with the local building control service.
The point for a rewire is that it is one piece of notifiable work, not one per circuit. If you are not registered with a competent person scheme, the building control body or third-party certifier has to be notified before work starts, which means before first fix, not before testing. What the customer gets at the end depends on the route: with a registered electrician, the guidance says the customer receives a Building Regulations Compliance Certificate within 30 days of the work being completed, alongside your Electrical Installation Certificate. Say on the quote which route you are using and what paperwork follows.
Old boards, ceilings and floors: asbestos
A rewire goes into the parts of a house where the Health and Safety Executive's guide to where asbestos is found, checked on 17 November 2026, says to look. It lists textiles "in fuse boxes behind the actual fuse", loose-fill insulation "between cavity walls, under floorboards and in loft spaces", and textured decorative coatings on ceilings and walls. Drilling and boring through textured coatings is on its list of lower-risk, non-licensed tasks, with task sheets in HSE's Asbestos essentials.
Look at the old board and the ceilings at the survey, before you price. If a sample has to go off for testing, say on the quote what happens to the programme: the rooms affected wait, and the dates for first fix there move. Price any work on it once you know what it is.
Write the exclusions down
A customer comparing three rewire quotes will compare the totals. An exclusions list is how they can tell whether yours covers more. On a rewire, the common ones are:
- Plastering, filling and decorating, unless you are doing them.
- Lifting and relaying fitted floor coverings and laminate.
- Moving furniture, if the customer has agreed to clear rooms.
- Faults in the supply or the network operator's equipment.
Where software helps
The per-point count is the part that keeps changing: during the walk-round, after the customer has talked it over at home, and sometimes again at first fix. Quoting software with line items you can edit and resend saves rewriting the quote each time. If the same tool books first and second fix as one job with a gap between them, the plasterer's dates and your stage invoice sit in one place. The software list has filters for optional quote lines, deposits and multi-day jobs.
Changes to make to your rewire quote template
- Add a per-point table, with rows for circuits, sockets, lighting, fixed appliances, alarms and bonding.
- Add a living-in line, and a question on your survey sheet asking whether the house will be occupied.
- Write your standard exclusions list once, and paste it into every rewire quote.
- Add a first fix stage to your payment schedule, and a line saying who plasters and how that affects your second fix date.
- Add a survey check of the old board and ceilings for asbestos, and the wording for what happens if a sample is needed.